| |
|
| |
June
2008 |
| |
10th - Receive first shipment
of grain |
| |
9th -13th NEDAK employees
receive Delta-T classroom training |
| |
|
| |
May
2008 |
| |
5th - NEDAK employees begin
classroom training |
| |
|
| |
March
2008 |
| |
Main
Process Building: |
| |
Working on the walls and ceiling for the office, lab
and control room areas |
| |
Started the walls on the switch gear area up stairs |
| |
DDE: |
| |
Insulating the last columns in that area |
| |
Still installing siding on the building |
| |
Installing fire sprinker piping inside the building |
| |
Grain
Handling: |
| |
Pouring concrete for tower pads |
| |
Started erecting Towers and bridges for the
distiller grains to the dryer |
| |
O'Neill
Site: |
| |
The office area and electrical room are almost
complete |
| |
Installed the heaters for the building |
| |
|
| |
Febuary
2008 |
| |
Main
Process Building: |
| |
Hanging steel for the centrifuge area and at the
office/switch gear area |
| |
Still running pipe thru-out the building |
| |
DDE: |
| |
Installing insulation on the columns |
| |
Installing fire sprinkler piping |
| |
Installing the siding and the roof |
| |
Balance
of Plant: |
| |
Working on installing the fire piping, pulling cable
thru-out the plant |
| |
O'Neill
Site: |
| |
Building is installed and started work inside for
the office |
| |
|
| |
January
2008 |
| |
Main
Process Building: |
| |
Erecting steeling for the office/switch gear area
and the centrifuge area |
| |
Running cable tray, pulling cable, installing more
lighting |
| |
Installing more pipe rack, piping setting the last
pieces of equipment |
| |
Fermentation
Area: |
| |
Setting control racks and pulling wire |
| |
Dryer: |
| |
Installing more steel and getting ready to install
more of the Dryer |
| |
Balance
of Plant: |
| |
Working on fire piping, completing ethanol storage,
working on the cooling tower
and installing the skin on the Boiler |
| |
O'Neill
Site: |
| |
Installing piping, erecting the building and
installing the fence |
| |
The paving and the ethanol storage liner is complete |
| |
|
| |
December
2007 |
| |
Main
Process Building: |
| |
Installing piping, valves and cable tray |
| |
Building sides and walls are complete |
| |
Set the CO2 Scrubber |
| |
Fermentation
Building: |
| |
Welding up pipe and supports |
| |
Installing cable tray |
| |
DDE: |
| |
Setting Columns, installing pipe and cable tray |
| |
Dryer
Area: |
| |
Installing dryer and dryer steel |
| |
Balance
of plant: |
| |
Welding up the ethanol storage tanks |
| |
Pouring wet distillers pad |
| |
O'Neill
Site: |
| |
Setting equipment, running pipe and electrical |
| |
Paving the roads |
| |
|
| |
November
2007 |
| |
Grain Handling:
|
| |
Working on running cable tray and pulling wire |
| |
|
| |
Installing
pipe rack steel and piping |
| |
Installing
skin on the building |
| |
Running cable tray lighting and pulling wire |
| |
Fermentation
Building: |
| |
Installing pipe, cable
tray, and conduit |
| |
DDE: |
| |
Set more equipment and
still hanging steel |
| |
Working on all the
electrical equipment in the switch gear building |
| |
Running more pipe rack
from main process to DDE and from DDE to ethanol
storage |
| |
Dryer/RTO
area: |
| |
RTO complete |
| |
Concrete complete |
| |
Installing steel and
dryer parts |
| |
Balance
of Plant: |
| |
Working
on Ethanol storage tanks |
| |
Site paving |
| |
Erected the fire water
tank and pump house |
| |
Started foundation on
Wet distillers pad |
| |
O'Neill Site: |
| |
Erected
the fire water tank |
| |
Start piping and electrical |
| |
Finishing up the rail |
| |
|
| |
October 2007 |
| |
Grain Handling:
|
| |
Working on installing lighting and electrical |
| |
Main
Process Building: |
| |
Setting the Centrifuges |
| |
Installing pipe rack and pipe |
| |
Fermentation
Building: |
| |
Installing steel, pipe and set equipment |
| |
DDE: |
| |
Installing steel, running pipe and
set equipment |
| |
The cooling tower is set and working on pump bases |
| |
Dryer and RTO foundations complete, starting to set
the RTO equipment |
| |
Working on foundations for the fire water tank, pump
house & boiler building |
| |
O'Neill Site: |
| |
Rail road almost complete & ethanol
storage tank is complete |
| |
|
| |
September 2007 |
| |
Grain Handling:
|
| |
Almost done, working on the electrical |
| |
Main
Process Building: |
| |
Pouring pump pad and centrifuge foundations |
| |
Fermentation
Building: |
| |
Installing steel and piping |
| |
DDE: |
| |
Installing steel and pump bases |
| |
O'Neill Site: |
| |
Ethanol tank installation is complete |
| |
Still running track thru town |
| |
Installing road crossing thru town |
| |
|
| |
August 2007 |
| |
Grain Handling:
|
| |
Installing dust handling equipment |
| |
Still working on the milling tower |
| |
Started installing electrical |
| |
Main
Process Building |
| |
Started erecting steel on the building |
| |
Started pouring the floor |
| |
Working
on the processing tank farm |
| |
Setting
steel in the DDE area |
| |
Installed
both truck scales |
| |
O'Neill Site: |
| |
Working on the ethanol storage tank |
| |
Laying train track
in town |
| |
Drill water well for the site |
| |
|
| |
July 2007 |
| |
Grain Handling:
|
| |
Reclaim Tower Complete |
| |
Spouting & Gates are Installed |
| |
Bulk Scale / Scalper / Mill Surge Bin Installed |
| |
Stairs, Catwalk, and Ladders are mostly complete |
| |
Footing
for the Main Process Building complete |
| |
Chemical
tanks are set, tank farm is being erected, and the
fermentation tanks have lids on |
| |
Excavating for the Dryer, Switch gear building, cool
tower and the ethanol storage area |
| |
Started
erecting the storage tank at the trans load site |
| |
|
| |
June 2007 |
| |
Grain Handling:
|
| |
Silo Bridge Installation |
| |
Hammermill Installation |
| |
Working on the Milling Tower |
| |
Still Excavating for the
Main Process Building and Pouring Concrete in the
DDE Area |
| |
NPPD
working on the Sub-Station |
| |
Started Excavating
O'Neil Train Loading Site |
| |
Working
On the Fermentation Tanks, Beerwell, Liquefaction
Tank, and the tanks in the tank
farm area |
| |
|
| |
May 2007 |
| |
Grain Handling:
|
| |
Installing equipment on the milling tower, hammer
mils, surge bin |
| |
Installing dust collection equipment |
| |
Installing steel, elevators and conveyers |
| |
Excavating for the main process building and the DDE
building |
| |
Underground piping about 85% complete |
| |
Still working on Fermentation tanks and beer well |
| |
Excavating and pouring tank farm foundations |
| |
NPPD started work on the switch yard |
| |
Started dirt work on the railroad at O'Neill |
| |
|
| |
April 2007 |
| |
Grain Handling:
Both grain bins finished |
| |
Installing conveyor in receiving pit |
| |
Installed walkway and distribution conveyer in DDGS
building |
| |
Installed truck receiving building |
| |
Installed milling tower steel |
| |
Excavating and pouring footers in Main Process
Building |
| |
Excavating and pouring foundation for North Boiler |
| |
Excavating and pouring foundation for DDE Building |
| |
Installing sewer, gas, fire hydrants, and water
piping |
| |
Erecting Fermentation Tanks 1,2, & 3, and Beer well |
| |
|
| |
March 2007 |
| |
The Administration
Building is 75% Complete |
| |
The DDGS Building is
65% Complete |
| |
The Truck Unloading
Pits are 90% Complete |
| |
The Fermentation
Foundations are 70% Complete |
| |
Fermentation Tanks are
Started |
| |
The Grain Bin
Foundations are Complete |
| |
Underground Utilities
are still underway |
| |
|
| |
February 2007 |
| |
The
Administration Building is 60% Complete |
| |
Maintenance
Building is erected and we're installing electrical
and gas heat in shop area |
| |
Foundations are
poured for DDGS Building, truck receiving pits,
grain bins, fermentation
building,
fermentation tanks, and beer well. |
| |
We're in the
process of erecting the DDG Building |
| |
Work on the
underground utilities has started. |
| |
|
| |
SEPTEMBER 28, 2006 |
|
| |
|
|
| |
AUGUST 31, 2006 |
Delta T announces
they will be the General Contractor |
| |
|
|
| |
AUGUST 14, 2006 |
Capital drive
exceeds $40,000,000
|
| |
|
|
| |
AUGUST 9, 2006 |
EPC Contract signed
at Delta-T in Williamsburg, VA.
|
| |
|
|
| |
AUGUST 7, 2006 |
|
| |
|
|
| |
JULY 2006 |
Capital Drive
Meetings.
|
| |
|
|
| |
JULY 2006 |
Ground Breaking.
|
| |
|
|
| |
JUNE 15, 2006 |
Effective with
Securities and Exchange Commission.
|
| |
|
|
| |
DECEMBER 2005 |
Registration of membership units filed with SEC on Dec. 15, 2005. Offering expected in Spring 2006.
|
| |
|
|
| |
NOVEMBER 2005 |
Delta T Phase 2 Contract signed
Road design in process with Nebraska Department of Roads and Gilmore and Associates
|
| |
|
|
| |
JUNE 2005 |
Business Plan Completed |
| |
|
|
| |
APRIL 2005 |
Agreement entered into with Cline, Williams, Wright, Johnson,
and Oldfather LLP to complete the offering. |
| |
|
Contract signed with HDR for permitting |
| |
|
|
| |
MARCH 2005 |
Project Development contract signed with Delta T |
| |
|
|
| |
JANUARY 2005 |
Formed Alliance with Delta T |
| |
|
|
| |
DECEMBER 2004 |
Consulting contract signed with Durante & Associates |
| |
|
|
| |
MARCH 2004 |
Pre-feasibility study performed by Durante and Associates
|
| |
|
Formed Alliance with Durante and Associates
|
| |
|
|
| |
DECEMBER 5 2003 |
Nedak Ethanol is organized as an LLC |
| |
|
|
| |
JUNE 2003 |
First organizational meeting |