Our Progress                             <-- Click Here To View Our Progress in Pictures -->            
 

U.S. SEC  Click here for Updates after August 2008

     

 

  • 10-K

  • 10-Q

  • 8-K

  • 10-Q/A

Audited Annual Financial Statement

Quarterly Reviewed Financial Statements

Public filing of miscellaneous information updates

Amended Quarterly Financial Statements

 

All information that is available from NEDAK is posted in these documents. 

The financial statements have comprehensive Notes and Management Discussion.

Please refer to these documents freely for answers to your questions.

   
  August 2008
 

Web update:    It has been some time since this web page has been updated.  NEDAK management apologizes for this delay.  The first priority must be to protect our investor’s interests and these recent three months have been full of critical issues as we approach mechanical completion and performance testing of the plant. 

Plant Status:    Because of the matters discussed below, construction completion of our ethanol plant has been delayed.  We now expect that we will commence operations at the plant in the fourth quarter of 2008. 

Construction Issues:  We have identified certain deficiencies in the construction of our ethanol plant which was expected to achieve mechanical completion by July 15, 2008.  After working with our contractor, Delta-T Corporation (“Delta”) to resolve those deficiencies, on August 4, 2008, we and Delta executed a Second Letter of Commitment and Intent (the “Second LOC”) which provides that we and Delta will negotiate in good faith to amend the Engineering, Procurement and Construction Services Fixed Price Contract (the “Contract”) dated August 9, 2006 with Delta to provide the following:  

 

·         Declare that the ethanol plant met Mechanical Completion as of the date of the Second LOC, July 28, 2008.

·         Performance Testing must be completed and Name Plate Production must be reached by sixty days after Mechanical Completion.

·         The incentive payment of $5,000,000 (which we agreed to pay Delta in April, 2008) will be deferred, payable by NEDAK 24 months after Performance Test Acceptance, plus interest.

·         Ethanol process Performance Testing will not include the dryer/ regenerative thermal oxidizer (“RTO”).  The dryer will be tested for guaranteed performance separately after it is completed.

·         Delta will pay liquidated damages if the ethanol plant does not meet its Name Plate Weekly Production within sixty days of Mechanical Completion.  Such payments would be calculated at thirty cents per gallon per week for each gallon that our weekly production is less than 850,000 gallons (Name Plate) per week.

·         The first portion of construction retainage was paid to Delta on Wednesday, August 6, 2008.

·         The rest of the retainer will be paid in increments upon completion of the following specified plant components:

o        Delta will engage an independent third-party engineer to certify that all tanks are “safe and functional” and that all tanks meet Nebraska Code requirements.  Any recommended changes by the engineer will be completed by Delta at Delta’s expense.

o        Insulation.

o        The dryer and performance demonstration.

o        The installation of the liner and gravel in the ethanol storage tank spill containment

o        Mechanical Completion punch-list completion.

·         Delta will cause the tank constructor to provide a ten-year warranty for the tanks, supported by a $500,000 guaranty of the owner of the tank constructor.

·         If any government regulatory agency finds that any tank in the petroleum product tank farm does not meet Nebraska Code requirements, then such deficiency will be covered by the warranty contained in the Contract.

 

Wind Damage:  On June 12, 2008, a severe wind burst damaged the RTO at the plant.  As of August 11, the damage has been repaired, but the delays required by the repairs may require that some of the first production of Distiller’s grain will be sold as wet product with discounted prices.

   
  June 2008
    10th - Receive first shipment of grain
    9th -13th NEDAK employees receive Delta-T classroom training
   
  May 2008
    5th - NEDAK employees begin classroom training
   
  March 2008
   Main Process Building:
    Working on the walls and ceiling for the office, lab and control room areas
    Started the walls on the switch gear area up stairs
   DDE:
    Insulating the last columns in that area
    Still installing siding on the building
    Installing fire sprinker piping inside the building
  Grain Handling:
    Pouring concrete for tower pads
    Started erecting Towers and bridges for the distiller grains to the dryer
   O'Neill Site:
    The office area and electrical room are almost complete
    Installed the heaters for the building
   
  Febuary 2008
   Main Process Building:
    Hanging steel for the centrifuge area and at the office/switch gear area
    Still running pipe thru-out the building
   DDE:
    Installing insulation on the columns
    Installing fire sprinkler piping
    Installing the siding and the roof
   Balance of Plant:
    Working on installing the fire piping, pulling cable thru-out the plant
   O'Neill Site:
    Building is installed and started work inside for the office
   
  January 2008
   Main Process Building:
    Erecting steeling for the office/switch gear area and the centrifuge area
    Running cable tray, pulling cable, installing more lighting
    Installing more pipe rack, piping setting the last pieces of equipment
   Fermentation Area:
    Setting control racks and pulling wire
   Dryer:
    Installing more steel and getting ready to install more of the Dryer
   Balance of Plant:
 

  Working on fire piping, completing ethanol storage, working on the cooling tower

  and installing the skin on the Boiler

   O'Neill Site:
    Installing piping, erecting the building and installing the fence
    The paving and the ethanol storage liner is complete
   
  December 2007
   Main Process Building:
    Installing piping, valves and cable tray
    Building sides and walls are complete
    Set the CO2 Scrubber
   Fermentation Building:
    Welding up pipe and supports
    Installing cable tray
   DDE:
    Setting Columns, installing pipe and cable tray
   Dryer Area:
    Installing dryer and dryer steel
   Balance of plant:
    Welding up the ethanol storage tanks
    Pouring wet distillers pad
   O'Neill Site:
    Setting equipment, running pipe and electrical
    Paving the roads
   
  November 2007
   Grain Handling:
      Working on running cable tray and pulling wire
   
      Installing pipe rack steel and piping
      Installing skin on the building
      Running cable tray lighting and pulling wire
   Fermentation Building:
      Installing pipe, cable tray, and conduit
   DDE:
       Set more equipment and still hanging steel
      Working on all the electrical equipment in the switch gear building
      Running more pipe rack from main process to DDE and from DDE to ethanol storage
   Dryer/RTO area:
       RTO complete
      Concrete complete
      Installing steel and dryer parts
   Balance of Plant:
      Working on Ethanol storage tanks
      Site paving
      Erected the fire water tank and pump house
      Started foundation on Wet distillers pad
   O'Neill Site:
 

    Erected the fire water tank

      Start piping and electrical
      Finishing up the rail
   
  October 2007
   Grain Handling:
      Working on installing lighting and electrical
   Main Process Building:
      Setting the Centrifuges
       Installing pipe rack and pipe
   Fermentation Building:
      Installing steel, pipe and set equipment
   DDE:
       Installing steel, running pipe and set equipment
      The cooling tower is set and working on pump bases
      Dryer and RTO foundations complete, starting to set the RTO equipment
      Working on foundations for the fire water tank, pump house & boiler building
   O'Neill Site:
 

     Rail road almost complete & ethanol storage tank is complete

   
  September 2007
   Grain Handling:
      Almost done, working on the electrical
   Main Process Building:
      Pouring pump pad and centrifuge foundations
   Fermentation Building:
      Installing steel and piping
   DDE:
       Installing steel and pump bases
   O'Neill Site:
       Ethanol tank installation is complete
       Still running track thru town
       Installing road crossing thru town
   
  August 2007
   Grain Handling:
      Installing dust handling equipment
      Still working on the milling tower
      Started installing electrical
   Main Process Building
      Started erecting steel on the building
      Started pouring the floor
   Working on the processing tank farm
   Setting steel in the DDE area
   Installed both truck scales
   O'Neill Site:
      Working on the ethanol storage tank
      Laying train track in town
      Drill water well for the site
   
  July 2007
   Grain Handling:
      Reclaim Tower Complete
      Spouting & Gates are Installed
      Bulk Scale / Scalper / Mill Surge Bin Installed
      Stairs, Catwalk, and Ladders are mostly complete
   Footing for the Main Process Building complete
   Chemical tanks are set, tank farm is being erected, and the fermentation tanks have lids on
   Excavating for the Dryer, Switch gear building, cool tower and the ethanol storage area
   Started erecting the storage tank at the trans load site
   
  June 2007
   Grain Handling:
      Silo Bridge Installation
      Hammermill Installation
      Working on the Milling Tower
   Still Excavating for the Main Process Building and Pouring Concrete in the DDE Area
   NPPD working on the Sub-Station
   Started Excavating O'Neil Train Loading Site
 

 Working On the Fermentation Tanks, Beerwell, Liquefaction Tank, and the tanks in the tank

 farm area

   
  May 2007
   Grain Handling:
      Installing equipment on the milling tower, hammer mils, surge bin
      Installing dust collection equipment
      Installing steel, elevators and conveyers
   Excavating for the main process building and the DDE building
   Underground piping about 85% complete
   Still working on Fermentation tanks and beer well
   Excavating and pouring tank farm foundations
   NPPD started work on the switch yard
   Started dirt work on the railroad at O'Neill
   
  April 2007
   Grain Handling: Both grain bins finished
      Installing conveyor in receiving pit
      Installed walkway and distribution conveyer in DDGS building
      Installed truck receiving building
      Installed milling tower steel
   Excavating and pouring footers in Main Process Building
   Excavating and pouring foundation for North Boiler
   Excavating and pouring foundation for DDE Building
   Installing sewer, gas, fire hydrants, and water piping
   Erecting Fermentation Tanks 1,2, & 3, and Beer well
   
  March 2007
   The Administration Building is 75% Complete
   The DDGS Building is 65% Complete
   The Truck Unloading Pits are 90% Complete
   The Fermentation Foundations are 70% Complete
   Fermentation Tanks are Started
   The Grain Bin Foundations are Complete
   Underground Utilities are still underway
   
  February 2007
   The Administration Building is 60% Complete
   Maintenance Building is erected and we're installing electrical and gas heat in shop area
 

 Foundations are poured for DDGS Building, truck receiving pits, grain bins, fermentation

 building, fermentation tanks, and beer well.

   We're in the process of erecting the DDG Building
   Work on the underground utilities has started.
   
  SEPTEMBER 28, 2006
     
  AUGUST 31, 2006

Delta T announces they will be the General Contractor

     
  AUGUST 14, 2006
Capital drive exceeds $40,000,000
     
  AUGUST 9, 2006
EPC Contract signed at Delta-T in Williamsburg, VA.
     
  AUGUST 7, 2006

Capital drive exceeds $35,000,000 - Escrow Broken.

 Investor Letter Announcing Escrow Met - 27KB PDF.

     
  JULY 2006
Capital Drive Meetings.
     
  JULY 2006
Ground Breaking.
     
  JUNE 15, 2006
Effective with Securities and Exchange Commission.
     
  DECEMBER 2005
Registration of membership units filed with SEC on Dec. 15, 2005.  Offering expected in Spring 2006.
     
  NOVEMBER 2005
Delta T Phase 2 Contract signed

Road design in process with Nebraska Department of Roads and Gilmore and Associates
     
  JUNE 2005 Business Plan Completed
     
  APRIL 2005 Agreement entered into with Cline, Williams, Wright, Johnson,
and Oldfather LLP to complete the offering.
    Contract signed with HDR for permitting
     
  MARCH 2005 Project Development contract signed with Delta T
     
  JANUARY 2005 Formed Alliance with Delta T
     
  DECEMBER 2004 Consulting contract signed with Durante & Associates
     
  MARCH 2004 Pre-feasibility study performed by Durante and Associates
    Formed Alliance with Durante and Associates
     
  DECEMBER 5 2003 Nedak Ethanol is organized as an LLC
     
  JUNE 2003 First organizational meeting